Customer:   National Petrochemical Industrial Co. (NATPET), Yanbu, Saudi Arabia
Client:   Lurgi AG, Frankfurt/Main, Germany
Project:   Construction of PDH plant. Member of commissioning team. Pre-commissioning and commissioning activities.
Position:   Commissioning Engineer
Date:   January 2007 till November 2008

Client:   Lurgi AG, Frankfurt/Main, Germany
Project:   Pre-/Commissioning Engineering for various petrochemical projects in Saudi-Arabia and Malaysia.
Position:   Commissioning Engineer
Date:   May till December 2006

Customer:   RWE Power AG, Pumped-storage power station Herdecke ("Koepchenwerk"), Germany
Client:   ARGEids-Dokumentations GmbH & Co. KG, Höchstadt an der Aisch, Germany
Project:   Re-organization of the on-site plant documentation in Herdecke pumped-storage power station.
Position:   Site Manager Re-Organization
Date:   January till March 2006

Customer:   RWE Power AG, Hydroelectric Power Plant Wintrich, Bernkastel-Kues Site, Germany
Client:   ARGEids-Dokumentations GmbH & Co. KG, Hoechstadt an der Aisch, Germany
Project:   Reorganization of the Wintrich Hydroelectric Power Plant documentation.
Position:   Re-Organization Site Manager
Date:   November till December 2005

Customer:   SLOVNAFT a.s., Bratislava, Slovak Republic
Client:   Linde-KCA-Dresden GmbH, Dresden, Germany
Project:   Construction of Polypropylene Plant PP3. Coordination of commissioning activities among client, customer and licenser.
Position:   Commissioning Coordinator
Date:   October 2004 till September 2005

Customer:   SLOVNAFT a.s., Bratislava, Slovak Republic
Client:   Linde-KCA-Dresden GmbH, Dresden, Germany
Project:   Construction of Polypropylene Plant PP3. Administration of piping material.
Position:   Material Manager
Date:   March till September 2004

Customer:   S.C. ROMPAK S.R.L, Pascani, Romania
Client:   ONDEO Industrial Solutions GmbH, Stuttgart, Germany
Project:   Construction of a biological wastewater treatment plant for a yeast manufacturer. Commissioning and warranty run of the plant.
Position:   Commissioning Manager
Date:   February 2004 and November 2003

Customer:   STMicroelectronics, Crolles, France
Client:   ONDEO Industrial Solutions GmbH, Stuttgart, Germany
Project:   Construction of a chemo-biological wastewater treatment plant for a chip-manufacturing plant. Commissioning of the plant.
Position:   Commissioning Engineer
Date:   December 2003 till January 2004